San Pablo Creek Culvert Repair Project
The work to be done generally consists of removing debris in the culvert, cleaning the culvert invert, preparing concrete surfaces and exposed rebar, installing new rebar along the culvert invert, overlaying the culvert invert, installing new concrete beam and steel struts, repairing storm drain connection to the culvert, and bypass of creek channel flows as necessary for construction.
Status
Bidding Closed
Prebid Date | 4/9/24 10:00am |
Bid Date | 4/23/24 2:00pm |
Location
City of Orinda
Engineer's cost estimate: $2,300,000
A pre-bid meeting will be held on Tuesday, April 9, 2024 at 10:00 a.m. at the entrance to the culvert at storage and staging Areas A1 & A3 to review project construction. Prospective bidders attendance is recommended but not mandatory.